Category archives for: Construction

Construction Update For the Week of 9/21/09

Construction Update For the Week of 9/21/09

This multi-faceted project will upgrade the old, unreliable infrastructure system and get the campus ready for future growth

Campus Infrastructure- Ventura Street is closed from Los Angeles Avenue to the South side of Bell Tower West. The North end of Ventura Street from Los Angeles Avenue to Santa Barbara Street has been re-opened to vehicular and pedestrian traffic. Contractors will be installing the new electrical, telephone, and data duct banks on Ventura Street. Hydronic piping through the North Quad is nearing completion.

Construction Update for the Week of 9/8/09

Construction Update for the Week of 9/8/09

This multi-faceted project will upgrade the old, unreliable infrastructure system and get the campus ready for future growth.

Construction Activities For the Week of 8/17/09

Construction Activities For the Week of 8/17/09

Published 8/14/2009
The following was forwarded to us by James Walsh, Manager of Construction Services at CSUCI
Construction activities are as follows for the week of 8/17/09:
Infrastructure:
This multi-faceted project will upgrade the old, unreliable infrastructure system and get the campus ready for future growth.
Central Plant – Exterior building plaster is nearing completion and the installation of new [...]